Afzal, F, Yunfei, S, Sajid, M and Afzal, F (2019) Integrated priority decision index for risk assessment in chaos: cost overruns in transport projects. Engineering, Construction and Architectural Management, 27(04), 825–49.

Bonanomi, M M, Hall, D M, Staub-French, S, Tucker, A and Talamo, C M L (2019) The impact of digital transformation on formal and informal organizational structures of large architecture and engineering firms. Engineering, Construction and Architectural Management, 27(04), 872–92.

Cole, R J (1999) Building environmental assessment methods: clarifying intentions. Building Research & Information, 27(04), 230–46.

Cole, R J (1999) Postscript: Green Building Challenge 2000. Building Research & Information, 27(04), 342–3.

Cole, R J and Larsson, N K (1999) GBC '98 and GBTool: background. Building Research & Information, 27(04), 221–9.

Cole, R J and Mitchell, L (1999) Customizing and using GBTool: two case-study projects. Building Research & Information, 27(04), 257–76.

Comet, C (2009) Social capital and profits of small firms in the French construction industry. Construction Management and Economics, 27(04), 411–8.

El-Sayegh, S M (2009) Multi-criteria decision support model for selecting the appropriate construction management at risk firm. Construction Management and Economics, 27(04), 385–98.

Feghaly, J, El Asmar, M, Ariaratnam, S and Bearup, W (2019) Selecting project delivery methods for water treatment plants. Engineering, Construction and Architectural Management, 27(04), 936–51.

Glaumann, M, Malm, T and Larsson, J (1999) Evaluation of green buildings in Sweden. Building Research & Information, 27(04), 276–85.

Kannimuthu, M, Raphael, B, Ekambaram, P and Kuppuswamy, A (2019) Comparing optimization modeling approaches for the multi-mode resource-constrained multi-project scheduling problem. Engineering, Construction and Architectural Management, 27(04), 893–916.

Li, H, Lu, W and Huang, T (2009) Rethinking project management and exploring virtual design and construction as a potential solution. Construction Management and Economics, 27(04), 363–71.

Lingard, H C, Cooke, T and Blismas, N (2009) Group-level safety climate in the Australian construction industry: within-group homogeneity and between-group differences in road construction and maintenance. Construction Management and Economics, 27(04), 419–32.

Liu, J and Cheah, C Y J (2009) Real option application in PPP/PFI project negotiation. Construction Management and Economics, 27(04), 331–42.

  • Type: Journal Article
  • Keywords: concession; negotiation; real option; public-private partnerships; private finance initiative
  • ISBN/ISSN: 0144-6193
  • URL: https://doi.org/10.1080/01446190902807071
  • Abstract:
    Over the past two decades, many developing countries have grown to become more familiar with the notions and the use of public–private partnership/private financing initiative (PPP/PFI) schemes in building large-scale infrastructure assets. However, owing to higher levels of complexity and longer contractual durations, PPP/PFI projects are often embedded with higher risks. On the one hand, any private sector concessionaire would strive to secure some forms of subsidies or guarantees from the host government to alleviate its risk concerns. On the other hand, the host government would also attempt to counterbalance the grant of these incentives by introducing additional ‘repayment’ obligations, such as placement of a cap on the tariff or toll rates. Modelled as real options, support and repayment features found in the case of a wastewater treatment plant in Southern China are evaluated using a combination of Monte Carlo simulation and spreadsheet-based cash flow models. The objective is to illustrate how a negotiation band incorporating these option values can be constructed, which would enlarge the feasible bargaining range for both parties. The risk implications of two disparate bidding scenarios found in the case will also be discussed.

Luo, M, Fan, H and Liu, G (2019) Measuring regional differences of construction productive efficiency in China. Engineering, Construction and Architectural Management, 27(04), 952–74.

Ma, H, Liu, Z, Zeng, S, Lin, H and Tam, V W (2019) Does megaproject social responsibility improve the sustainability of the construction industry?. Engineering, Construction and Architectural Management, 27(04), 975–96.

Manoliadis, O G, Pantouvakis, J-P and Christodoulou, S E (2009) Improving qualifications-based selection by use of the fuzzy Delphi method. Construction Management and Economics, 27(04), 373–84.

Rees, W E (1999) The built environment and the ecosphere: a global perspective. Building Research & Information, 27(04), 206–20.

Smyth, H and Fitch, T (2009) Application of relationship marketing and management: a large contractor case study. Construction Management and Economics, 27(04), 399–410.

Todd, J A and Geissler, S (1999) Regional and cultural issues in environmental performance assessment for buildings. Building Research & Information, 27(04), 247–56.

Tone, K, Skitmore, M and Wong, J K W (2009) An investigation of the impact of cross-cultural communication on the management of construction projects in Samoa. Construction Management and Economics, 27(04), 343–61.

Viles, E, Rudeli, N C and Santilli, A (2019) Causes of delay in construction projects: a quantitative analysis. Engineering, Construction and Architectural Management, 27(04), 917–35.

Wang, S, Tang, J, Zou, Y and Zhou, Q (2019) Research on production process optimization of precast concrete component factory based on value stream mapping. Engineering, Construction and Architectural Management, 27(04), 850–71.