Chung, T H, Abraham, D M and Gokhale, S B (2004) Decision Support System for Microtunneling Applications. Journal of Construction Engineering and Management, 130(06), 835–43.

  • Type: Journal Article
  • Keywords: Microtunneling; Economic factors; Soil conditions; Decision support systems; Pipelines;
  • ISBN/ISSN: 0733-9364
  • URL: https://doi.org/10.1061/(ASCE)0733-9364(2004)130:6(835)
  • Abstract:
    Microtunneling is a trenchless technology method used for installing new pipelines. The inherent advantages of this method over open-cut trenching have led to its increasing use since its first introduction into North America in the early 1980s. With this technology, surface disruption can be minimized, especially in urban areas, and high accuracy of installation (usually less than 2cm over 100m) can be achieved in both line and grade. But microtunneling machines are very expensive and few contractors have extensive experience with this technology. Microtunneling can also be risky when unexpected obstacles or soil changes occur. Careful constructability analysis is needed, and an appropriate microtunneling method should be selected in order to achieve successful completion of microtunneling projects. A computerized decision support system (DSS) for microtunneling was developed to support decision making for contractors who want to bid on microtunneling projects. This paper discusses the decision-making process for microtunneling and the development of the DSS. When the user enters basic information about the potential project such as drive length, installation depth, pipe diameter, and soil condition, the DSS evaluates whether microtunneling will be economically feasible and suggests appropriate types of microtunneling methods. The user can then select microtunneling machines, types of pipes, and types of shaft construction methods. This DSS is most beneficial when used at the preplanning stage by utility contractors.